Comparison of European Interconnection and Operation Requirements for Wind Farms

Authors

  • Marcela-Martnez-Rojas Author
  • Andreas Sumper Author
  • Oriol-Gomis-Bellmunt Author
  • Roberto-Villafa la-Robles Author
  • Eduard-Valsera-Naranjo Author
  • Antoni-Sudria Author

DOI:

https://doi.org/10.24084/repqj07.455

Keywords:

Wind farm, grid code, connection requirements, voltage control, frequency control

Abstract

The necessity to provide clean energy, along with the latest technology developments in the eld of wind turbines, have been re ected by building bigger wind farms. This, combined with the integrated operation be tween wind farms and the grid, involves all the electric sys tem a ecting di erent aspects as transitory stability, volt age regulation, energy reserve management and the electric market. Most UE transmission system operators (TSO) have responded introducing technical regulations for wind farm interconnections. The present paper presents a com parison of some European grid codes for wind farms (WF), and their operative implications.

Author Biographies

  • Marcela-Martnez-Rojas

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

  • Andreas Sumper

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

  • Oriol-Gomis-Bellmunt

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

  • Roberto-Villafa la-Robles

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

  • Eduard-Valsera-Naranjo

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

  • Antoni-Sudria

    CITCEA-UPC. E.U. d' Enginyeria Técnica Industrial de Barcelona- Departamento de Ingeniería 
    Eléctrica. Spain

Downloads

Published

2024-01-24

Issue

Section

Articles